February
18, 2004
Juan
Sanchez, Chair
Monterey County Planning Commission
Monterey County Planning and Building Inspection Department
2620 First Avenue
Marina, CA 93933
RE:
Proposed DArrigo Brothers Agricultural Processing Facility
(PLN020069)
Meeting
Date: February 25, 2004
Dear
Chairperson Sanchez and Members of the Planning Commission:
LandWatch Monterey County is once again writing to urge your Commission
either to deny the proposed DArrigo Brothers agricultural
processing facility and office building, or to take no action to
approve the project until after the Commission has reviewed a full
Environmental Impact Report (EIR).
LandWatch
made this same request last December, and we were delighted that
the Commission did not approve the proposed project at that time.
We were sorry, however, that the County did not immediately proceed
with the preparation of a full EIR. We know that the applicant is
eager to bring its proposed project forward for a decision, but
what was true in December remains true today. Prior to any approval
of the project, the California Environmental Quality Act (CEQA)
requires the preparation of a full EIR.
CEQA
Issues
LandWatch has submitted an extensive letter on the most recent version
of the Notice of Intent to Adopt a Mitigated Negative Declaration
for the proposed DArrigo project. As that letter shows, the
proposed project might cause a number significant environmental
impacts. Under state law, when significant environmental impacts
might be caused by a proposed project, neither the Commission nor
the Board of Supervisors can shortcut the environmental
review process mandated by CEQA. A full EIR must be prepared. The
process involved in the preparation and review of a Mitigated
Negative Declaration is in no way equivalent to the process
involved in the preparation of a full Environmental Impact Report.
The full EIR process requires the publication of a Draft
EIR, the provision of a substantial period to allow the public to
review and comment on that Draft, and then a required
response by the County to each one of the comments made. The Final
EIR must include the Draft, the comments received, and
the responses to those comments.
The
courts have been very clear that if a proposed project may
have a significant impact on the environment, a full EIR must be
prepared. State law is also clear that substantial evidence
means any substantial evidence. The Revised Initial
Study and Notice of Intention To Adopt A Mitigated Negative Declaration
does not include an actual mitigated negative declaration, demonstrating
that all of the identified impacts have been reduced to the point
of insignificance, and does not, in any other way, demonstrate the
lack of any possible negative environmental impact. Given this,
and as we hope this letter and our more extensive comment letter
make clear, CEQA requires that a full EIR be prepared.
Unless
and until the Commission has such a Final EIR before
it, it cannot legally vote to approve the proposed project. It can
vote to turn it down, but not to approve it. If the Commission
determines to take action on the proposed project without a full
Environmental Impact Report, we urge the Commission to deny the
project.
Two
Fundamental Reasons to Deny the Proposed Project
1.
Incompatibility With The Farmland Security Zone
This
proposed project is fundamentally inconsistent with the Farmland
Security Zone that exists on the subject property. On December
2, 2003, the Board of Supervisors (without environmental review,
and certainly over our objections) made a determination that building
the proposed facilities on property subject to a Farmland Security
Zone contract was permissible, because the proposed facilities
were consistent with the purposes of the contract.
While the Planning Commission has not been asked to pass on the
consistency of the proposed project with the Farmland Security
Zone contract covering the land, we think that the Commission
needs to understand the issues involved, and that the Commission
can and should consider whether it is appropriate to build the
kind of facilities proposed on lands that have been enforceably
restricted to maintain their agricultural production. The Planning
Commission has an independent duty to make sure that the County
of Monterey follows state law requirements, as it makes decisions
about whether or not to approve a proposed project.
We
strongly believe that developing a large scale agricultural factory
(including a major office building) on prime, commercially productive
farmland covered by a Farmland Security Zone contract is not
consistent with the purposes of the Farmland Security Zone,
nor is it consistent with the provisions of the contract. We also
think it is clear that the Countys list of compatible
uses does not allow the construction of the proposed large scale
agricultural processing facility and office building on property
subject to a Farmland Security Zone contract.
The
staff report presented to the Planning Commission says that the
proposed use would be consistent with the Principles of
Compatibility stated in Section 51238.1(a) of the California Government
Code regarding development on lands subject to the Williamson
Act. The text of that section is reproduced below. We believe
that the Commission will find, upon reading the language of the
Code, that the staff report has reached an erroneous conclusion:
51238.1.
(a) Uses approved on contracted lands shall be consistent with
all of the following principles of compatibility:
(1)
The use will not significantly compromise the long-term productive
agricultural capability of the subject contracted parcel or
parcels or on other contracted lands in agricultural preserves.
(2)
The use will not significantly displace or impair current
or reasonably foreseeable agricultural operations on the subject
contracted parcel or parcels or on other contracted lands
in agricultural preserves. Uses that significantly displace
agricultural operations on the subject contracted parcel or
parcels may be deemed compatible if they relate directly to
the production of commercial agricultural products on the
subject contracted parcel or parcels or neighboring lands,
including activities such as harvesting, processing, or shipping.
(3)
The use will not result in the significant removal of adjacent
contracted land from agricultural or open-space use.
In
evaluating compatibility a board or council shall consider the
impacts on noncontracted lands in the agricultural preserve
or preserves.
We
believe that it is obvious that the proposed factory and office
building will significantly compromise the long-term productive
agricultural capability of the
parcel, and that it
will significantly displace
current
agricultural
operations on the
parcel. In fact, the project will
take twenty-seven acres of prime, commercially productive agricultural
land out of production. This is the opposite of what the FSZ is
supposed to achieve.
We
also think that the Commission should closely review the language
of the Countys list of compatible uses, for lands subject
to a Farmland Security Zone contract. Unless a use is specifically
included on this list, the use is not compatible. Here is the
language relied upon by DArrigo Brothers:
1.
The drying, packing or other processing of an agricultural commodity
usually performed on the premises where it is produced
but not including slaughter houses, fertilizer yards, bone yards
or plants for the reduction of animal or vegetable matter (emphasis
added).
It
is obvious that the processing proposed is not usually performed
on the premises. In fact, as the application materials submitted
to the County show, processing of commodities produced on the
premises is now (usually) performed in Castroville, an urban and
industrial areaand just the kind of area in which agricultural
processing facilities are appropriate, and permitted. Not only
are the products grown on the premises not now processed on site,
but the proposal is to process commodities grown throughout Monterey
County. Further, the office building component of the proposed
project has nothing to do with the processing of an agricultural
commodity.
If
the County contract were construed to say what DArrigo wants
it to say, then this would mean that all agricultural lands located
in Monterey County on which a Farmland Security Zone contract
has been recorded would be deemed appropriate for large scale
agricultural processing. The requested determination would also
mean that farmland owners could build large office buildings on
lands subject to a Farmland Security Zone contract. Such an interpretation
would fundamentally change the nature of land uses throughout
the County. The possible impacts of this change (one not legally
supportable under the current contract) would be extremely significant,
and must be analyzed in a full Environmental Impact Report, prior
to any decision that could have this result.
As
the Planning Commission undoubtedly knows, DArrigo Brothers
has received significant property tax benefits by promising to
abide by the provisions of state law relating to a restriction
of possible uses in Farmland Security Zones. The Department of
Conservation has written to the county about this matter, and
properly cites what the state and the county are supposed to receive
in return for the tax benefits provided. As state law has been
cited by the Department of Conservation, compatibility
exists only when (a) the use will not significantly compromise
long term productive agricultural capability of the subject contracted
parcels or other contracted land in preserves; 2) obstruct or
displace potential agricultural operations, or 3) induce non-agricultural
development of prime farmland. These principles are to achieve
the original purpose of Williamson Act contracts to preserve
the maximum amount of the limited supply of agricultural land
[Government Code Section 51220(a)].
Allowing
the placement of the proposed processing facility and office building
on the DArrigo lands, which are encumbered by a Farmland
Security Zone contract, would violate each one of the above principles.
Approval would immediately displace existing agricultural production
on the contracted parcels. It would displace future agricultural
use of this prime land. And the interpretation recommended by
County Counsel would induce nonagricultural development
of prime farmland. Thus, the proposed application must be
denied.
2.
Inconsistency With the Current General Plan
The
proposed project is inconsistent with provisions of the current
Monterey County General Plan. As such, it cannot be approved.
Specifically, the proposed project is inconsistent with Section
30.0.8 of the Greater Salinas Area Plan. That Section says this:
Agricultural
Support Services (coolers, Cold rooms, loading docks and farm
equipment shops) may be allowed, subject to obtaining a use
permit, on lands designated as "Farmlands", provided
that the following findings are made based upon substantial
evidence in each case:
a.
That the land on which the support facilities are proposed
is not suitable for cultivation due to terrain, soil
or other physical constraints.
b.
That such support facilities are necessary or appropriate
in connection with the cultivation, harvesting or processing
of crops raised by the applicant on same [sic] portions of
the subject property.
c.
That the maintenance and operation of such support facilities
will not impair the ability to produce crops on the balance
of the subject property or on neighboring properties.
Support
facilities allowed under this policy shall be subject to the
following standards:
a.
Such support facilities may be used in connection with the
cultivation, harvesting, processing or storage of crops grown
on the subject property or crops grown by the applicant or
by others on lands in close proximity to the subject property,
particularly when such action would retain or increase the
amount of farmland for crop production.
b.
The land on which such support facilities are constructed
shall no [sic] be subdivided from the balance of the subject
property.
c.
Such support facilities be compatible with land uses on
neighboring properties.
[Emphasis added]
The
proposed project is fundamentally inconsistent with these General
Plan provisions, just as it is fundamentally inconsistent with
the Farmland Security Zone on the property. The land involved
is eminently suitable for cultivation. The applicant
is not proposing to process crops that are grown on some
portions of the subject property, or by others on lands
in close proximity to the subject property. Because of its
inconsistency with these General Plan provisions, the proposed
project must be denied.
Conclusion
We believe that the Planning Commission should deny the proposed
project, because of its fundamental incompatibility with the Monterey
County General Plan, and because of its violation of the state law,
local ordinance, and contract provisions that govern what uses are
permissible on lands designated as Farmland Security Zone.
If the Commission chooses not to deny the project, then it must
consider a full EIR, prior to voting to approve the project.
We
think that the legal provisions relating to this proposed project
are clear. We trust that the Commission will not choose to disregard
them.
Thank
you for taking our views into consideration.
cc: |
Members,
Monterey County Board of Supervisors
Planning Staff
County Counsel
Spreckels Residents Association
State Department of Conservation |
[Return
to Spreckels Issues and Actions]
posted
02.17.04
|